A project manager is reviewing project documentation and finds the following statement: 'The weather during the construction phase will be favorable.' This statement is best classified as:
An assumption is something considered to be true without proof or demonstration. In this case, the statement about favorable weather during construction is taking something for granted without having evidence that it will actually occur. This is a classic example of an assumption in project management.
Comparative analysis of other options:
A risk would be an uncertain event that, if it occurs, has a positive or negative effect on project objectives (e.g., "Poor weather might delay construction").
An issue is a current problem that requires resolution (e.g., "We are currently experiencing weather delays").
A constraint is a limitation or restriction that affects project performance (e.g., "Construction must be completed during the summer months").
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are common examples of assumptions in project management?
Open an interactive chat with Bash
How can assumptions impact the outcome of a project?
Open an interactive chat with Bash
What is the process of identifying and managing assumptions in a project?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access