A project manager is reviewing the progress of a project. The planned value (PV) is $80,000, and the earned value (EV) is $70,000. Based on this information, what is the schedule variance (SV)?
Schedule variance (SV) is calculated using the formula SV = EV - PV. Substituting the given values:
SV = $70,000 - $80,000 = -$10,000.
Therefore, the schedule variance is -$10,000. A negative SV indicates that less work has been completed than planned at this point in the schedule. The incorrect options may result from common calculation errors, such as reversing the order of subtraction (which would yield $10,000), adding the values instead of subtracting (resulting in $150,000), or confusing SV with the EV value ($70,000). Understanding the correct formula and calculation method is essential for accurate schedule performance assessment.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the significance of schedule variance (SV)?
Open an interactive chat with Bash
How do you calculate earned value (EV)?
Open an interactive chat with Bash
What are the implications of a negative schedule variance?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access