A project manager is transitioning a team's detailed work plan from a traditional approach to an adaptive framework. What is the best way to reorganize the work elements for effective use in iterations?

  • Assign work elements directly to team members based on their expertise.

  • Convert the work elements into user stories and prioritize them in a product backlog.

  • Group the work elements into larger work packages for high-level tracking.

  • Arrange the work elements in a sequential order and break up into sprints.

CAPM
Agile Frameworks/Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot