A project manager needs to record information about parties involved in a project, including their levels of interest, power, and influence. Which project document should be used for this purpose?
The stakeholder register is the document used to record detailed information about all stakeholders, including their interests, power, influence, and impact on the project. This helps the project manager plan effective stakeholder engagement strategies. The risk register documents identified risks and their responses, not stakeholder details. The communications management plan outlines how communications will be managed but does not contain stakeholder-specific information. The issue log tracks problems that arise during the project, not stakeholder data.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What specific information is included in a stakeholder register?
Open an interactive chat with Bash
How does a project manager use the stakeholder register to engage stakeholders?
Open an interactive chat with Bash
What is the difference between a stakeholder register and a risk register?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access