A project manager needs to track all alterations to the project schedule and costs in a predictive, plan-based project. Which project artifact should they use to document these changes?
The Change Log is the appropriate artifact for documenting all approved changes to the project, including schedule and cost alterations. It serves as a central repository for tracking changes and ensures transparency among stakeholders. The Quality Management Plan describes how the project's quality requirements will be met but does not track changes. The Requirements Traceability Matrix links requirements to deliverables, and the Communication Management Plan outlines how project communications will be managed; neither is used to document changes to schedule and costs.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a Change Log and why is it important?
Open an interactive chat with Bash
How does a Change Log differ from other project management documents?
Open an interactive chat with Bash
What are some best practices for maintaining a Change Log?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access