CAPM Practice Question

A Scrum team is preparing to plan the next sprint and needs to decide what work to include. What should they use as the primary input to determine the scope of the upcoming sprint?

  • A detailed work breakdown structure prepared by the project manager.

  • The technical specifications document created during project initiation.

  • The project's comprehensive Gantt chart.

  • The list of priority items provided by the product owner, called a product backlog.

CAPM
Agile Frameworks/Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot