A Scrum team is preparing to plan the next sprint and needs to decide what work to include. What should they use as the primary input to determine the scope of the upcoming sprint?
The list of priority items provided by the product owner, called a product backlog.
A detailed work breakdown structure prepared by the project manager.
The project's comprehensive Gantt chart.
The technical specifications document created during project initiation.
In Scrum, the team uses the list of priority items provided by the product owner, known as the product backlog, as the primary input for sprint planning. The team selects items from the top of this prioritized list based on their capacity. A detailed work breakdown structure (WBS) and Gantt chart are tools from predictive methodologies and are not typically used in agile projects. Technical specifications from project initiation may not reflect the current priorities and are less relevant for sprint planning.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a product backlog?
Open an interactive chat with Bash
How does a Scrum team prioritize items in the product backlog?
Open an interactive chat with Bash
What is the role of the product owner in Scrum?
Open an interactive chat with Bash
CAPM
Agile Frameworks/Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access