CAPM Practice Question
A Work Breakdown Structure (WBS) is used to break down the project scope into manageable work packages, but it does not depict the sequencing of activities.
True
False
A Work Breakdown Structure (WBS) is used to break down the project scope into manageable work packages, but it does not depict the sequencing of activities.
True
False
True. The WBS is a hierarchical decomposition of the total scope of work that outlines what needs to be done to complete the project deliverables. It breaks down the project into smaller, more manageable components called work packages. However, it does not show the order in which tasks are to be performed or the dependencies between activities—that is handled by project scheduling tools and techniques such as Gantt charts and network diagrams.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.