After developing a communication plan for your project, what is the most appropriate way to respond to this planned strategy to ensure effective communication among stakeholders?
Stick strictly to the original communication plan without making any changes
Only communicate with the project sponsor to save time
Share project updates only at the end of the project to avoid confusion
Implement the communication plan and incorporate feedback from stakeholders
Implementing the communication plan and incorporating feedback from stakeholders is the appropriate response. This approach ensures that communication remains effective and adapts to the stakeholders' needs throughout the project. Strictly adhering to the original plan without adjustments may overlook changes in stakeholder requirements. Limiting communication to only the project sponsor or waiting until the project's end neglects the importance of keeping all stakeholders informed regularly.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a communication plan in project management?
Open an interactive chat with Bash
Why is stakeholder feedback important in a communication plan?
Open an interactive chat with Bash
What are common communication methods used in project management?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access