CAPM Practice Question
An adaptive project plan often incorporates iterative development cycles. Which component of the Scrum methodology aligns with this approach?
Sprints
Critical Path Method (CPM)
Gantt Charts
Work Breakdown Structure (WBS)
An adaptive project plan often incorporates iterative development cycles. Which component of the Scrum methodology aligns with this approach?
Sprints
Critical Path Method (CPM)
Gantt Charts
Work Breakdown Structure (WBS)
In Scrum, Sprints are fixed-length iterations that enable teams to develop and deliver increments of a product within a set period. This iterative approach allows for regular reassessment and adaptation of the project plan based on feedback and changing requirements, embodying the principles of adaptive planning. On the other hand, Gantt Charts, Work Breakdown Structure (WBS), and Critical Path Method (CPM) are tools commonly associated with predictive, plan-based methodologies. They focus on detailed upfront planning and sequential execution, which do not inherently support the flexibility and iterative cycles of adaptive approaches.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.