An organization is undertaking a project to produce a routine product with established processes and clear requirements. The project environment is stable, and stakeholders do not anticipate significant changes. Which project management approach would be most appropriate for this project?
Agile approach focused on flexibility
Hybrid approach combining predictive and agile methods
A predictive, plan-based approach is most appropriate when project requirements are well-understood, the scope is defined, and the environment is stable. In this scenario, the project involves a routine product with clear requirements and established processes, making a predictive approach suitable. Agile or iterative approaches are better suited for projects where requirements are expected to evolve or where flexibility is needed.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are the key characteristics of a predictive project management approach?
Open an interactive chat with Bash
What is the difference between predictive and agile project management?
Open an interactive chat with Bash
Can you explain what is meant by a stable project environment?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access