As a business analyst on a project that is shifting from a predictive plan-based methodology to an adaptive approach, which adjustment should you make to your business analysis process?
Concentrate on predictive modeling to identify all risks in advance.
Increase stakeholder collaboration to refine requirements throughout the project.
Limit stakeholder involvement after initial planning to maintain scope.
Finalize all requirements documentation before development begins.
In an adaptive methodology, increasing stakeholder collaboration to iteratively refine requirements is essential. This allows the project to adapt to changes and ensures that the product meets the evolving needs of stakeholders. Finalizing all requirements upfront is typical of predictive methodologies and does not accommodate changes well. Limiting stakeholder involvement contradicts the collaborative nature of adaptive approaches. Focusing solely on predictive modeling is less effective in adaptive environments where flexibility and ongoing adjustment are important.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is meant by an adaptive approach in project management?
Open an interactive chat with Bash
Why is stakeholder collaboration important in an adaptive methodology?
Open an interactive chat with Bash
What are the risks of finalizing requirements before development in adaptive projects?
Open an interactive chat with Bash
CAPM
Business Analysis Frameworks
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access