As a project manager for a construction project, you learn that a new environmental regulation could affect your project's operations. How should you use the stakeholder register to address this situation?
Adjust the project schedule to allow time for implementing necessary changes
Consult the stakeholder register to identify and engage stakeholders related to environmental compliance
Revise the project scope to accommodate compliance with the new regulation
Update the risk register to include the new environmental regulation as a potential risk
The stakeholder register is a tool that lists all project stakeholders along with their interests, influence, and roles. By consulting the stakeholder register to identify and engage stakeholders related to environmental compliance, you ensure that the right individuals are informed and involved in addressing the new regulation. Updating the risk register is important but does not directly involve the stakeholder register. Revising the project scope or schedule might be necessary later but should be done after consulting the relevant stakeholders.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a stakeholder register?
Open an interactive chat with Bash
How do you identify stakeholders related to environmental compliance?
Open an interactive chat with Bash
What should be done after identifying stakeholders in the register?
Open an interactive chat with Bash
CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access