As a project manager leading an adaptive project, which approach best aligns with interpreting the success criteria of a task?

  • Measure success by strictly following the initial scope and schedule without considering evolving requirements

  • Evaluate success by minimizing changes requested by stakeholders during the project

  • Collaborate with stakeholders to define success criteria that focus on delivering value and accommodating changes

  • Define success criteria based on the completion of detailed upfront planning and documentation

CAPM
Agile Frameworks/Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot