As a project manager working on implementing a new project management software, you are compiling a list of stakeholders. Which of the following should be considered an external stakeholder when planning stakeholder engagement?
The software vendor's project consultant is not an employee of the organization and is therefore an external stakeholder. External stakeholders are individuals or groups outside the company who can affect or be affected by the project. Internal stakeholders, such as the operations manager, IT support team, and human resources director, are employees within the organization.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What defines an external stakeholder in project management?
Open an interactive chat with Bash
Can you explain why the software vendor's project consultant is considered an external stakeholder?
Open an interactive chat with Bash
What are some examples of internal and external stakeholders?
Open an interactive chat with Bash
CAPM
Business Analysis Frameworks
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access