Defining project scope is a typical activity within the Initiating process group.
True
False
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Bash, the Crucial Exams Chat Bot
AI Bot
Defining project scope is a typical activity within the Initiating process group.
True
False
This statement is false. Defining project scope is a typical activity within the Planning process group, not the Initiating process group. The Initiating process group focuses on activities like developing the project charter and identifying stakeholders. Defining scope is part of planning how the project will be executed and is therefore conducted during the Planning phase.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.