CAPM Practice Question

During project execution, a key stakeholder requests a change that affects the project scope. What should the project manager do first in response to this change request?

  • Inform the stakeholder that changes are not allowed at this stage as the scope was agreed upon at the beginning of the project.

  • Submit the change request to the change control board for review.

  • Implement the change to satisfy the stakeholder.

  • Adjust the project schedule to accommodate the change.

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot