During project planning, a manager creates a hierarchical representation of all the work that needs to be completed for the project. What project component is this?
The hierarchical representation of all the work to be completed is the Work Breakdown Structure (WBS). The WBS breaks down the project scope into manageable sections and deliverables, facilitating better planning, execution, and control. The Project Scope Statement describes the project's scope, major deliverables, assumptions, and constraints but does not provide a hierarchical breakdown. The Project Schedule outlines timelines and sequencing of activities but doesn't represent the decomposition of scope into work packages. The Project Charter is a document that formally authorizes the project and outlines initial requirements but does not detail all the work.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a Work Breakdown Structure (WBS)?
Open an interactive chat with Bash
How do you create a Work Breakdown Structure?
Open an interactive chat with Bash
What role does a Project Scope Statement play?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access