In a predictive, plan-based project, which technique is most suitable for calculating and documenting deviations from the project baseline related to both cost and schedule performance?
Earned Value Management (EVM) is the most appropriate technique for calculating and documenting deviations from the project baseline regarding cost and schedule performance. EVM integrates scope, schedule, and cost parameters to assess project performance and progress. It provides quantitative data on cost variance (CV) and schedule variance (SV), allowing project managers to identify and address deviations effectively. Other options like Critical Path Method focus on scheduling but do not directly provide variance calculations, while Risk Analysis and Quality Audits serve different purposes in project management.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are the key components of Earned Value Management (EVM)?
Open an interactive chat with Bash
How is Cost Variance (CV) calculated and what does it indicate?
Open an interactive chat with Bash
Can you explain the difference between Schedule Variance (SV) and the Critical Path Method (CPM)?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access