In adaptive project management, what is the logical unit used to structure work within iterations?
Milestones
Tasks
Phases
Sprints
CAPM
Agile Frameworks/Methodologies
Your Score:
Bash, the Crucial Exams Chat Bot
AI Bot
In adaptive project management, what is the logical unit used to structure work within iterations?
Milestones
Tasks
Phases
Sprints
In adaptive methodologies like Scrum, the iteration is structured as a 'Sprint', which is a fixed period during which specific work is completed and reviewed. 'Phases' are typically associated with predictive, plan-based approaches. 'Tasks' are individual pieces of work within a Sprint but do not define the structure of the iteration itself. 'Milestones' are significant events or deliverables in the project timeline but are not used to structure iterations.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.