CAPM Practice Question
In adaptive project management, which artifact is crucial for determining scope during iteration planning?
Project charter
Prioritized product backlog
Work Breakdown Structure (WBS)
Detailed requirements documentation
In adaptive project management, which artifact is crucial for determining scope during iteration planning?
Project charter
Prioritized product backlog
Work Breakdown Structure (WBS)
Detailed requirements documentation
In adaptive (Agile) projects, the prioritized product backlog is the crucial artifact for determining scope during iteration planning. It contains an ordered list of features or user stories prioritized based on customer value, guiding the team on what to develop next. Detailed requirements documentation and a work breakdown structure are techniques more aligned with predictive, plan-based projects. A project charter authorizes the project but does not provide the detailed scope needed for iteration planning.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.