CAPM Practice Question
In adaptive project management, which technique is commonly used to prioritize tasks based on their value and urgency to stakeholders?
MoSCoW method
Pareto Analysis
Critical Path Method
Earned Value Management
In adaptive project management, which technique is commonly used to prioritize tasks based on their value and urgency to stakeholders?
MoSCoW method
Pareto Analysis
Critical Path Method
Earned Value Management
The MoSCoW method is used in adaptive project management to prioritize tasks by categorizing them into Must have, Should have, Could have, and Won't have. This helps teams focus on delivering the most valuable and urgent tasks first. The other options are not specifically used for task prioritization in adaptive projects: the Critical Path Method is used in predictive project management for scheduling, Earned Value Management is for performance measurement, and Pareto Analysis identifies the most significant factors affecting outcomes.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.