In an adaptive project, a product manager needs to prioritize backlog items for the next iteration. The team aims to maximize value delivered to the customer while considering the effort required for each item. Which prioritization technique should the project manager use?
Use Earned Value Management to rank tasks
Assign higher priority to tasks with the earliest deadlines
Schedule tasks based on team members' availability
Prioritize items by dividing their business value by their estimated effort
The product manager should prioritize items by dividing their business value by their estimated effort. This is known as the Weighted Shortest Job First (WSJF) technique. It helps the team focus on tasks that provide the highest value in the shortest time, optimizing resource use and customer satisfaction. Assigning priority based on deadlines is less effective in adaptive projects, where timelines are flexible. Scheduling tasks based on team availability doesn't consider value delivery. Earned Value Management is a performance measurement technique suitable for predictive projects, not for prioritizing tasks in adaptive environments.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the Weighted Shortest Job First (WSJF) technique?
Open an interactive chat with Bash
Why is it important to prioritize backlog items based on value and effort?
Open an interactive chat with Bash
What are some common mistakes when prioritizing tasks in agile projects?
Open an interactive chat with Bash
CAPM
Agile Frameworks/Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access