In an adaptive project, a product manager needs to prioritize backlog items for the next iteration. The team aims to maximize value delivered to the customer while considering the effort required for each item. Which prioritization technique should the project manager use?

  • Schedule tasks based on team members' availability

  • Prioritize items by dividing their business value by their estimated effort

  • Use Earned Value Management to rank tasks

  • Assign higher priority to tasks with the earliest deadlines

CAPM
Agile Frameworks/Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot