CAPM Practice Question

In an adaptive project, your team has completed a feature during an iteration. The feature functions as expected and passes all planned tests. During the review meeting, a stakeholder requests additional functionalities to be added to this feature. How should you interpret the completion status of this task?

  • The task is not complete because it does not include the stakeholder's new functionalities.

  • The task needs assessment based on stakeholder feedback indicating additional work.

  • The team can evaluate whether to pause progress until the new functionalities are addressed.

  • The task met its initial goals since it satisfied the objectives established prior to the iteration.

CAPM
Agile Frameworks/Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot