CAPM Practice Question
In an Agile team, who is responsible for maximizing the value delivered by managing the backlog and prioritizing tasks?
Scrum Master
Process Owner
Project Manager
Product Owner
In an Agile team, who is responsible for maximizing the value delivered by managing the backlog and prioritizing tasks?
Scrum Master
Process Owner
Project Manager
Product Owner
The Product Owner is responsible for maximizing the value delivered by the development team in an Agile environment. They manage the product backlog and prioritize tasks based on business value and stakeholder needs. The Scrum Master facilitates the Agile process and removes impediments but does not prioritize tasks. The Project Manager oversees project execution but does not typically manage task prioritization in Agile teams. The Process Owner focuses on optimizing business processes, not managing the backlog.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.