In project schedule management, which sequence of activities dictates the project's earliest finish date because delays in these activities will delay the entire project?
The critical path is the sequence of activities that determines the shortest time in which a project can be completed. Any delay in activities on the critical path will directly impact the project's end date because there is zero float. Other paths may have float, allowing for some flexibility without affecting the overall project duration.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the critical path methodology?
Open an interactive chat with Bash
What does it mean for an activity to have zero float?
Open an interactive chat with Bash
How do you calculate the critical path in a project?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access