The statement is false. In the Critical Path Method (CPM), the critical path is the longest sequence of activities through a project network diagram. It determines the shortest possible duration to complete the project, as any delays in these activities will directly affect the project's finish date. Understanding this helps in identifying tasks that cannot be delayed without impacting the overall project schedule.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the Critical Path Method (CPM)?
Open an interactive chat with Bash
What are dependent tasks in project management?
Open an interactive chat with Bash
How can understanding the critical path benefit project management?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access