CAPM Practice Question

In project scheduling using the Critical Path Method (CPM), what does the critical path represent?

  • The collection of all tasks with some available float time

  • The sequence of activities with the highest costs

  • The sequence of activities that affect the project completion date if delayed

  • The shortest sequence of tasks considering dependencies