In project scheduling, what term describes the sequence of tasks that determines the shortest possible duration to complete a project?
Critical path
Gantt chart
Resource leveling
Work breakdown structure
In project scheduling, what term describes the sequence of tasks that determines the shortest possible duration to complete a project?
Critical path
Gantt chart
Resource leveling
Work breakdown structure
The critical path represents the longest sequence of tasks in a project plan that must be completed on time for the project to finish by its due date. It determines the shortest possible project duration because any delays in critical path tasks will directly delay the entire project. Understanding the critical path helps project managers identify essential tasks that impact the project timeline.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.