The correct answer is the longest sequence of tasks that cannot be delayed without delaying the entire project, known as the critical path. The critical path dictates the minimum project duration because any delay in these tasks will directly impact the project's finish date. Other sequences may have float or slack, allowing for delays without affecting the overall schedule.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the critical path in project management?
Open an interactive chat with Bash
What are slack and float in project scheduling?
Open an interactive chat with Bash
How can I identify the critical path in a project schedule?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies