CAPM Practice Question
Which artifact is commonly used in adaptive projects to track the remaining work in a sprint and is updated daily to reflect the team's progress?
Project Charter
Gantt Chart
Network Diagram
Burndown Chart
Which artifact is commonly used in adaptive projects to track the remaining work in a sprint and is updated daily to reflect the team's progress?
Project Charter
Gantt Chart
Network Diagram
Burndown Chart
A Burndown Chart is an artifact used in adaptive projects to track the amount of work remaining in a sprint. It is updated daily and provides a visual representation of the team's progress, helping the team adjust and plan accordingly. Gantt Charts and Network Diagrams are planning tools commonly used in predictive, plan-based projects to map out schedules and dependencies but are not typically updated daily to reflect sprint progress. A Project Charter is a document that authorizes the project but does not track daily progress.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.