CAPM Practice Question

Which of the following BEST describes a key responsibility that differentiates the project sponsor from the project team?

  • Providing high-level direction and securing resources for the project.

  • Ensuring that project objectives are met by completing assigned tasks.

  • Managing project risks and issues on a daily basis.

  • Developing the project schedule and coordinating team activities.

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot