CAPM Practice Question

Which of the following BEST describes the function of a Work Breakdown Structure (WBS) in project management?

  • It organizes project deliverables into manageable sections.

  • It allocates project resources to specific tasks.

  • It provides detailed scheduling of project activities.

  • It sequences project activities in the order they will be performed.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot