CAPM Practice Question

Which of the following BEST describes the purpose of a Work Breakdown Structure (WBS) in project management?

  • To define the detailed project schedule with all tasks and activities sequenced over time.

  • To provide a hierarchical decomposition of the total scope of work to be carried out by the project team.

  • To allocate resources to project activities and estimate costs accordingly.

  • To monitor project progress and control schedule variance.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot