Which project management document is used to track project requirements from their origin through fulfillment, ensuring that every requirement is accounted for throughout the project lifecycle?
The requirements traceability matrix is used to track and ensure that all project requirements are addressed throughout the project lifecycle. It links each requirement to its origin and traces it through development to final implementation, ensuring nothing is overlooked. Other documents like the work breakdown structure, project charter, and stakeholder register serve different purposes and do not specifically track requirements in this manner.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a requirements traceability matrix (RTM)?
Open an interactive chat with Bash
Why is it important to track requirements throughout the project lifecycle?
Open an interactive chat with Bash
What are some other project management documents and their purposes?
Open an interactive chat with Bash
CAPM
Business Analysis Frameworks
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access