Project Management Professional Practice Question
A project activity has an Early Start (ES) of 5 days and a Late Start (LS) of 8 days. What is the Float for this activity?
8 days
3 days
5 days
13 days
A project activity has an Early Start (ES) of 5 days and a Late Start (LS) of 8 days. What is the Float for this activity?
8 days
3 days
5 days
13 days
The correct answer is 3 days. Float, also known as slack, is the amount of time an activity can be delayed without affecting the project's overall schedule. It can be calculated using two formulas:
In this question, we are given the Early Start (ES) and Late Start (LS) values. Using the first formula:
Float = LS - ES Float = 8 - 5 Float = 3 days
This means the activity can be delayed by up to 3 days without impacting the project's completion date. Understanding float is crucial for project managers as it helps in prioritizing tasks, managing resources, and identifying potential schedule risks.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.