Project Management Professional Practice Question
A project activity has an Early Start (ES) of Day 5 and a Late Start (LS) of Day 8. What is the total float for this activity?
5 days
3 days
2 days
8 days
A project activity has an Early Start (ES) of Day 5 and a Late Start (LS) of Day 8. What is the total float for this activity?
5 days
3 days
2 days
8 days
The correct answer is 3 days. Float, also known as slack, is the amount of time an activity can be delayed without impacting the project's overall schedule. It can be calculated using two formulas:
In this case, we are given the Early Start (ES) and Late Start (LS) values. Using the first formula:
Float = LS - ES Float = 8 - 5 Float = 3 days
This means the activity can be delayed by up to 3 days without affecting the project's critical path or end date. Understanding float is essential for project managers to prioritize tasks, allocate resources efficiently, and manage schedule risks.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.