Project Management Professional Practice Question

A project has a Budget at Completion (BAC) of $200,000. The project is currently 40% complete according to the project schedule, but the actual work performed indicates an earned value (EV) of $70,000. What is the Schedule Variance (SV)?

  • $10,000

  • -$10,000

  • -$70,000

  • $70,000

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot