A project manager is analyzing the network diagram for a construction project. Activity X has a duration of 5 days and must be completed before the project can finish. If the project must be completed in 20 days, what is the Late Start (LS) for Activity X?
The correct answer is 15 days. To calculate the Late Start (LS) for Activity X, we need to work backwards from the project completion date. Since the project must be completed in 20 days and Activity X has a duration of 5 days, the latest time it can start without delaying the project is 15 days after the project start. This allows the activity to finish exactly when the project needs to be completed (20 - 5 = 15). If Activity X started any later, it would push the project completion beyond the required 20 days. Understanding Late Start is crucial for project managers as it helps identify the flexibility in scheduling activities that are not on the critical path.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is Late Start (LS) in project management?
Open an interactive chat with Bash
How does the Late Start affect project scheduling?
Open an interactive chat with Bash
What is the critical path method and how does it relate to Late Start?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access