A project manager is assessing risks for a new software development project. One identified risk has a probability of 0.6 and an impact rating of 0.8 on a scale from 0 to 1. What is the risk score for this particular risk?
The correct answer is 0.48. The risk score is calculated by multiplying the probability of the risk occurring by its impact. In this case, the probability is 0.6 and the impact is 0.8. Therefore, the risk score is 0.6 x 0.8 = 0.48.
This calculation helps project managers prioritize risks based on their overall significance to the project. A higher risk score indicates a more critical risk that may require immediate attention or more robust mitigation strategies. Understanding how to calculate risk scores is essential for effective risk management and decision-making throughout the project lifecycle.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
How is the probability of a risk determined in project management?
Open an interactive chat with Bash
What factors influence the impact rating of a risk?
Open an interactive chat with Bash
Why is calculating a risk score important for project managers?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access