Project Management Professional Practice Question

A project manager is estimating the duration of an activity. The optimistic estimate is 6 days, the most likely estimate is 10 days, and the pessimistic estimate is 20 days. The expected duration using the PERT (Program Evaluation and Review Technique) formula is 11 days.

  • False

  • True

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot