A project manager is using three-point estimation to calculate the variance for a critical project activity. The optimistic estimate is 10 days, and the pessimistic estimate is 22 days. What is the variance for this activity?
The correct answer is 4 days². The formula for calculating variance in three-point estimation is Variance = ((Pessimistic - Optimistic) / 6)². In this case, we have:
It's important to note that variance is expressed in squared units (days² in this case) and represents the spread of possible outcomes around the mean. A higher variance indicates greater uncertainty in the activity duration. Understanding how to calculate variance helps project managers quantify risks and make informed decisions about contingency planning and resource allocation.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is three-point estimation?
Open an interactive chat with Bash
Why is variance calculated in squared units?
Open an interactive chat with Bash
How does variance impact project risk management?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access