A project manager notices that a key stakeholder has been unresponsive and appears disengaged in recent meetings. The project manager decides to address this issue using emotional intelligence. What is the BEST initial step the project manager should take?
Send an informal email to the stakeholder to check in on their status.
Ignore the issue for now and hope the stakeholder re-engages on their own.
Schedule a one-on-one meeting with the stakeholder to understand their concerns.
Bring up the issue in the next team meeting to address it publicly.
The best initial step for the project manager is to have a one-on-one meeting with the stakeholder to understand their concerns. This approach demonstrates empathy and allows for open communication. Directly addressing the stakeholder's feelings and points of view can help identify the root cause of their disengagement. Simply sending an informal email lacks the personal touch and may not convey genuine interest. Publicly discussing the issue could embarrass or alienate the stakeholder further. Avoiding the issue does not solve the underlying problem.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is emotional intelligence in the context of project management?
Open an interactive chat with Bash
Why is a one-on-one meeting more effective than sending an email?
Open an interactive chat with Bash
What might be potential reasons for a stakeholder's disengagement?
Open an interactive chat with Bash
Project Management Professional
People
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access