An agile team seeks to enhance their sprint planning by accurately forecasting how much product backlog work they can likely accomplish in the next sprint. Which metric would provide the best foundation for their sprint capacity planning?
Velocity is the key agile metric utilized to gauge how much work an Agile team can complete in a sprint, where work is typically measured in story points or other units. It is calculated from historical data of previous sprints. This predictive measure helps teams estimate their future sprint capacity based on past performance, thus proving the most relevant for capacity planning during sprint planning.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is Velocity in Agile?
Open an interactive chat with Bash
How is Velocity calculated?
Open an interactive chat with Bash
Why are Burn-down and Burn-up charts used?
Open an interactive chat with Bash
Project Management Professional
Agile
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access