Project Management Professional Practice Question

As a project manager, you are in the process of planning your project's procurement activities. Your project requires highly specialized consulting services, which only a few suppliers can provide. To ensure that the selected supplier meets the project's needs, what is the best approach to take during the procurement process?

  • Use a Request for Information (RFI) to gather possible suppliers capable of providing the consulting services

  • Directly issue a contract to a supplier based on past engagements without a formal procurement document

  • Prepare a Request for Quotation (RFQ) focusing strictly on the price of the consulting services

  • Develop a Request for Proposal (RFP) that clearly outlines the project requirements and expected outcomes

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot