Project Management Professional Practice Question

As a project manager, you have identified a stakeholder who has high influence over project outcomes but low interest in the day-to-day operations of the project. Which of the following actions would be most appropriate to manage this stakeholder?

  • Exclude them from communications and updates, as they do not have a high interest in the project

  • Keep them informed through periodic high-level updates about project progress

  • Involve them in the decision-making process for day-to-day operations of the project

  • Provide them with frequent, detailed communications to ensure they are fully informed

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot