Project Management Professional Practice Question
During project agreement negotiations, assessing priorities and determining the ultimate objective(s) is unnecessary if both parties appear to be in general agreement.
True
False
During project agreement negotiations, assessing priorities and determining the ultimate objective(s) is unnecessary if both parties appear to be in general agreement.
True
False
This statement is false because even when both parties seem to generally agree, it's still crucial to assess priorities and clearly determine the ultimate objectives. This ensures that the agreement is based on a shared understanding and commitment to the project's goals, avoiding ambiguity that could lead to issues later on. Negotiations are a strategic process that requires careful consideration of all aspects, including priorities and objectives, to reach a successful and binding agreement.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.