Project Management Professional Practice Question

During the execution of an IT infrastructure upgrade project, you have identified a mix of internal and external stakeholders with varying degrees of power and interest. Which of the following steps would be MOST effective for your next action to ensure a robust stakeholder engagement strategy?

  • Send out weekly project updates via a newsletter to all stakeholders to keep them informed of project progress and decisions.

  • Schedule a one-time meeting with all stakeholders to obtain their buy-in and then focus solely on the project execution.

  • Develop and implement a tailored engagement plan for each category of stakeholders and periodically validate its effectiveness through feedback and stakeholder responses.

  • Review the stakeholder engagement plan to ensure it aligns with the latest project schedule and communication frequency.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot