Project Management Professional Practice Question

During the execution phase of a construction project, the project manager notices that the cost incurred for the procurement of materials is consistently exceeding the planned budget. What is the BEST course of action for the project manager to take?

  • Analyze the cause of the budget overrun, report to the governance board, and seek approval for budget adjustments.

  • Negotiate a discount with suppliers to reduce the costs of materials.

  • Ignore the variance as long as the overall project is within the approved budget.

  • Apply cuts to other areas of the project to counterbalance the overrun.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot